https://doi.org/10.1007/978-3-642-17989-1Electrical Networks; GEP; Matlab; NEP; PSP; Power System Planning; SEP; Transmissionexcursion 发表于 2025-3-27 04:43:34
Power System Planning, Basic Principles,ing a large number of countries, or even continents. Nowadays, an electric power system is one of the man-made largest scale systems; ever made, comprising of huge number of components; starting from low power electric appliances to very high power giant turbo-generators. Running this very large sys座右铭 发表于 2025-3-27 09:18:35
Optimization Techniques,ent) can be determined. For instance, in an ., the active power generations of power plants may be the decision variables. The dependent variables can be the total fuel consumption, system losses, etc. which can be calculated upon determining the decision variables. In a ., the locations and the siz诱骗 发表于 2025-3-27 10:21:53
http://reply.papertrans.cn/31/3057/305680/305680_34.png半球 发表于 2025-3-27 16:50:29
Load Forecasting, other words, such as, demand and consumption are also used instead of load, we use load as the most common term. The actual term is electric load; however, electric is omitted here and assumed to be obvious. It is well understood that both the energy (MWh, kWh) and the power (MW, kW) are the two ba向下 发表于 2025-3-27 21:05:12
http://reply.papertrans.cn/31/3057/305680/305680_36.png抚育 发表于 2025-3-27 22:32:15
Substation Expansion Planning, with the least costs, various operational constraints are met. In the so-called Substation Expansion Planning (SEP), the problem is to determine the required expansion capacities of the existing substations as well as the locations and the sizes of new substations together with the required availab缩短 发表于 2025-3-28 02:16:10
Network Expansion Planning, a Basic Approach,ns were, somehow, accounted for, the modeling was very approximate and needs much further investigations. The so called . (NEP) process tries to find the optimum routes between the generation buses (determined in GEP phase) and the load centers (determined from load forecasting) via substations (det知识分子 发表于 2025-3-28 06:53:55
http://reply.papertrans.cn/31/3057/305680/305680_39.pngExtemporize 发表于 2025-3-28 11:41:40
Reactive Power Planning,tudes are, normally, of main concern, during the last, perhaps, two decades, voltage stability is also received attention in literature. In this section, we try to briefly, differentiate between these two aspects of voltage performance of a system. Following that, we review some of the indices which